Project Title: Western Europe & Iceland Expedition
Project Start Date: 25/2019
Project Finish Date: 25/2019
Budget: $35,000.00
The four members of the Scott family will visit five countries within three weeks using a budget of $35,000. The plan will include a detailed itinerary with time and cost considerations for travel to the departing seaport, return trip, room and board, planned locations to visit, budget for individual activities, and a comprehensive cost breakdown.
| Name | Role | Position | Contact Information | 
|---|---|---|---|
| Dean Slocum | Project Manager | Oversees all aspects of project. | Phone, Email, SMS | 
| Bill Scott | Father, Sponsor, Customer | Primary contact in establishing project details. | Phone, Email, SMS | 
| Alexandra Scott | Mother, Sponsor, Customer | Secondary contact in establishing project details. | Phone, Email | 
| Nick Scott | Son, Customer | Provides input. | N/A | 
| Corey Scott | Son | Provides input. | N/A | 
| Requirements | Communication Needs | Frequency of Communication | Expectations | Influence on the Project | Interest and Power | 
|---|---|---|---|---|---|
| Book Flights | High | Weekly | $7,383.00 | High | High | 
| Book Cruise | High | Weekly | $10,980.00 | High | High | 
| Passports | High | Weekly | $600.00 | High | High | 
| Transportation | Medium | Weekly | $1,500.00 | Medium | Medium | 
| Excursions | High | Weekly | $5,000.00 | High | High | 
| Souvenirs | Low | Weekly | $1,000.00 | Medium | Medium | 
| Emergency Funds | High | Weekly | $1,000.00 | Low | Low | 
| Interest | Power | Classification | 
|---|---|---|
| High | High | Manage Closely | 
| Medium | Medium | Keep Informed | 
| Low | Low | Monitor | 
| Information Provider | Recipient(s) | Frequency | Medium | Location | |
|---|---|---|---|---|---|
| Status Report | PM | Family | Weekly | SharePoint | |
| Booking Confirmations | PM | Family | Once | SharePoint | |
| Passport Confirmations | Family | PM | Once | Email/Mail | SharePoint | 
PM: Project Manager
WBS: Work Breakdown Structure
| Risk | Probability (L,M,H) | Severity (L,M,H) | Mitigation Approach | 
|---|---|---|---|
| Project Manager skills not adequate | M | H | Project manager requires further training | 
| Failure to properly manage in accordance with family’s expectations | M | H | Keep open lines of constant communication | 
| Flight delays | M | H | Constant flight updates | 
| Cruise delays | M | M | Constant cruise updates | 
| Funding not properly allocated | L | H | Keep open lines of constant communication | 
Key:
Yellow = Low Risk
Orange = Medium Risk
Red = High Risk